鞍钢技术2024,Issue(3) :64-68.DOI:10.3969/j.issn.1006-4613.2024.03.0012

炼钢厂210 t冶金铸造起重机变频改造实践

Practice of Upgrading Frequency Conversion for 210 t Metallurgical Casting Crane in Steelmaking Plant

孙文华 彭占双 丛培起 纪斌
鞍钢技术2024,Issue(3) :64-68.DOI:10.3969/j.issn.1006-4613.2024.03.0012

炼钢厂210 t冶金铸造起重机变频改造实践

Practice of Upgrading Frequency Conversion for 210 t Metallurgical Casting Crane in Steelmaking Plant

孙文华 1彭占双 1丛培起 1纪斌1
扫码查看

作者信息

  • 1. 鞍钢集团朝阳钢铁有限公司,辽宁朝阳 122000
  • 折叠

摘要

针对炼钢厂210 t冶金铸造起重机原调压调速电机控制故障率高、检修维护量大等问题,进行了起重机变频改造.将起重机各机构的绕线式电机改造为变频电机,不需要维护碳刷及滑环,取消了换相和加速接触器,变频启停速度平稳顺滑,延长了机械设备使用寿命,提高了电机效率,避免了能源浪费.改造后,系统故障率降低80%左右,每年可节省综合费用总计约26.75万元.

Abstract

With regard to these problems such as high failure rates and heavy maintenance workload occurred in control of the old pressure-regulating and speed-regulating motor for the 210 t metallurgical casting crane in the steelmaking plant,upgrading the frequency conversion for the crane was carried out.Specifically,all wound-type motors for various mechanisms to the crane were transformed into variable-frequency motors,which did not need maintenance of carbon brushes and slip rings.And furthermore,the phase conversion and accelerating contactors were re-moved.Therefore,variable-frequency starting or stopping speed was stable and smooth,which ex-tended the service life of mechanical equipment,improved the motor efficiency and energy waste was avoided.After upgrading,the system failure rate was reduced by about 80%,and annual com-prehensive costs of approximately 267.5 thousand yuan could be saved.

关键词

炼钢/冶金铸造起重机/变频电机/系统故障率

Key words

steelmaking/metallurgical casting crane/variable-frequency motor/system fail-ure rate