水电工程缆机固定端主机房全地下布置研究与应用

扫码查看
某水电站拦河坝位于峡谷河段,两岸地形陡峻,建设中为了降低工程投资,将缆机机房布置于地下,通过上导向轮将牵引及提升系统由竖井引入地下机房,形成了完整的缆机动力及索道系统.该布置形式不仅解决了高边坡的开挖、支护和安全稳定及环保、水保等诸多问题,还降低了工程量和工程投资.本工程的成功经验可为今后缆机设计与安装提供参考和借鉴.
Research on layout of underground main machine room for cable crane with fixed end and applica-tion in hydropower project
A hydropower dam is located in the canyon reach and the terrain on both sides is steep.To re-duce project investment,the main room for cable crane is set underground.By use of upper guide pulley and through the shaft,the hauling system and hoisting system are transported into the underground room to provide power and cableway.This scheme not only can solve technical problems such as excavation and support of high slope,environmental protection and conservation of water and soil,but also can re-duce investment and work amount,which is worthy of reference.

underground main machine roomshaftanchor hole typecable crane

杨春旭

展开 >

华能澜沧江水电股份有限公司黄登·大华桥电厂,云南 怒江,671406

地下主机房 竖井 锚洞式 缆索起重机

2024

大坝与安全
中国水力发电工程学会 国家电力公司大坝安全监察中心

大坝与安全

影响因子:0.2
ISSN:1671-1092
年,卷(期):2024.(5)