首页|500kV变电站主变例行检修标准化作业流程

500kV变电站主变例行检修标准化作业流程

扫码查看
以 500 kV汾湖变 1 号主变例行检修为例,从主变检修周期、作业风险和停电前、停电期间、复电后各阶段详细介绍 500 kV变电站主变例行检修标准化作业流程,以期为作业安全、质量、进度的管控水平的提升提供参考.
Standardized Work Flow of Routine Maintenance for 500 kV Substation Transformers
This paper takes the No.1 transformer of 500 kV Fenhu substation as an exemplary case and elaborates in detail standardized work flow of routine maintenance for 500 kV substation transformers from the perspectives such as MT ma-intenance cycle,operational risks,and the work stages of pre-outage,intra-outage and post-outage.It may provide useful information for the promotion of management and control of work safety,quality and progression with respect to routine maintenance of main transformers with 500 kV and other voltage levels.

500 kV substationtransformerroutine maintenancestandardized work flow

黄秀娟、潘成程、沙俊民、席钰佳、邓超、王周杰

展开 >

国网浙江省电力有限公司超高压分公司,浙江 杭州 310000

500 kV变电站 主变 例行检修 标准作业流程

2024

电工技术
重庆西南信息有限公司(原科技部西南信息中心)

电工技术

影响因子:0.177
ISSN:1002-1388
年,卷(期):2024.(3)