电工技术2024,Issue(3) :195-197.DOI:10.19768/j.cnki.dgjs.2024.03.053

一起定子接地故障过程及原因分析

Report of an Actual Stator Grounding Fault and Causal Analysis

庞宏强 史振利 郭小勤
电工技术2024,Issue(3) :195-197.DOI:10.19768/j.cnki.dgjs.2024.03.053

一起定子接地故障过程及原因分析

Report of an Actual Stator Grounding Fault and Causal Analysis

庞宏强 1史振利 2郭小勤1
扫码查看

作者信息

  • 1. 西安益通热工技术服务有限责任公司,陕西 西安 710032
  • 2. 西安热工研究院有限公司,陕西 西安 710032
  • 折叠

摘要

针对某水电厂在试运期间出现的"发电机起停机保护"和"定子接地保护动作"故障现象进行分析,采用接地电阻和电压计算方法,准确判断故障相别,缩小故障排查范围,进一步结合故障点准确定位,验证了计算公式的正确性及有效性.通过事故分析、排查和故障点定位的处理过程,提出一种区分定子一次设备接地与二次回路接地的方法,为电站运行维护人员解决实际故障问题提供思路.

Abstract

This paper reports an actual fault with"generator startup and shutdown protection"and"stator grounding pro-tection activation"encountered by an actual hydroplant during trial operation.It describes the procedure performed for lo-cating the fault point,including determining fault phase and narrowing scope of fault cause,and verifies correctness and effectiveness of the calculation formula of grounding resistance and potential used in the procedure.It thereby highlights a method to distinguish between primary equipment grounding and secondary circuit grounding of stator through the afore-mentioned process of treating the fault,so as to provide useful inspiration for plants'operation and maintenance person-nel.

关键词

短路/接地/绝缘

Key words

short circuit/grounding/insulation