Process Research on the Nuclear Power Generator Rotor Installation by a Single Crane
Rotor installation is one of the most im-portant processes during the generator assembling.Large-size generators typically use two cranes to install the rotor.Based upon the configuration of the workshop crane,it is no way to use two cranes to install the rotor in a domestic nu-clear power plant.In order to solve the problem,according to the actual working conditions on site,the corresponding rotor installation process by a single crane is developed.This article introduces the nuclear power generator rotor in-stallation process by a single crane in detail,especially,fo-cus on the dedicated tools and the key points in the process of the scene execution and internal verification in the plant.