扫码查看
建设新型电力系统,需要以电网的智能化、信息化、数字化为基础.智能化变电站采用先进的信息技术、网络通信技术,是建设新型电力系统的重点.而做好智能变电站设备的二次安装调试至关重要.文章分析了智能变电站二次系统的结构,指出了二次系统安装调试的工作内容,提出了施工前应开展的准备工作,并对施工的重点和要点进行了分析,对相关工作具有一定的参考价值.
Technical Analysis of Installation and Debugging of Secondary System of Intelligent Substation
The construction of the new-type power system needs to be based on the intelligence,informatization and digitization of the power grid.Intelligent substation adopts advanced information technology and network communication technology,which is the focus of the construction of new-type power system.It is very important to do a good job in the secondary equipment installation and debugging of intelligent substation.This paper analyzes the structure of the secondary system of the intelligent substation,points out the work content of the installation and debugging,puts forward the preparatory work that should be carried out before construction,and analyzes the key points of installation and debugging technology,which has certain reference value for related work.

intelligent substationsecondary systeminstallation and debugging

樊建鹏

展开 >

山西运能电力科技有限公司,山西 运城 044000

智能变电站 二次系统 安装调试