ROV Flushing Burial Method for 35kV Submarine Cable Laying in Offshore Wind Farm
The power transmission from offshore wind farms relies on submarine cables,which can be installed using burial plow method or underwater remotely operating vehicle(ROV)flushing burial method.In comparison to conventional cable laying approaches,the ROV flushing burial method offers time-saving and efficiency im-provements,resulting in a reduction of over 30%in the construction period for each cable.The construction of the ROV flushing burial method of the submarine cable mainly includes the steps of construction ship positioning,sub-marine cable detection and positioning,and mud flushing and suction construction.The operation process and pre-cautions of each construction step are introduced in detail to ensure that the buried depth of submarine cable meets the design requirements.