国外某660 MW燃煤电站项目煤仓疏松装置的优化

Optimization of Coal Bunker Loose Device in Oversea 660MW Coal-fired Plant

由聪
电站系统工程2024,Vol.40Issue(6) :23-24.

国外某660 MW燃煤电站项目煤仓疏松装置的优化

Optimization of Coal Bunker Loose Device in Oversea 660MW Coal-fired Plant

由聪1
扫码查看

作者信息

  • 1. 中国电建集团北京院
  • 折叠

摘要

针对国外某660 MW燃煤电站的12座燃煤仓下部配置的疏松装置进行优化研究,对3种处理方案在基本原理、电耗、气耗等方面进行可行性和经济性的比较和分析,以便更好地了解3种方案的优缺点.

Abstract

The optimization research of the loose devices installed at the bottom of 12 coal bunkers in a 660MW coal-fired power plant abroad is carried out.Three treatment schemes are compared and analyzed in terms of basic principles,power consumption,gas consumption,etc.aspects in terms of feasibility and economy,so that understand the advantages and disadvantages of the three schemes.

关键词

煤仓/疏松装置/优化

Key words

coal bunker/loose device/optimization