沿海地区不均匀地质下大体量桩基施工组织
Construction Organization of Massive Pile Foundation Under Uneven Geology in Coastal Areas
李聪聪 1杨高勇 1唐明成 1张乐乐 1袁龙彬1
作者信息
- 1. 中国建筑第二工程局有限公司华南公司珠海分公司,广东珠海 519000
- 折叠
摘要
结合实际工程施工资料,分析沿海地区不均匀地质下大体量桩基施工,从多单位交叉施工协调,多种桩基类型的先后施工顺序,施工穿插的施工组织,以及施工时场内交通组织,特殊部位的场地处理,桩基检测的分区提前插入等进行描述,明确如何在有限场地内进行大体量桩基施工,从而实现不同区域、不同桩型同步施工,节约工程工期.
Abstract
Based on the actual engineering construction data,this paper analyzes the massive pile foundation construction under the uneven geology in the coastal areas,from the cross-construction coordination of multiple units,construction sequence of multiple pile foundation types,construction interspersed construction organization;The traffic organization in the field,the site treatment of special parts,and the partition and inserted in advance of pile foundation detection,to determine how to carry out large-volume pile foundation construction in a limited site,so as to realize the synchronous construction of different areas and different pile types,save the project duration.
关键词
大体量多种桩型施工/施工穿插/施工组织/平面布置Key words
large volume and multiple pile types construction/construction intersperse/construction organization/plane layout引用本文复制引用
出版年
2023