工程造价管理2024,Vol.35Issue(6) :34-38.DOI:10.19730/j.cnki.1008-2166.2024-06-034

基于承包商视角的电建工程索赔事件发现方法研究——以火力发电工程为例

Research on the Method of Discovering Power Construction Engineering Claims from the Perspective of Contractors——Taking Thermal Power Generation Engineering As an Example

杨凯
工程造价管理2024,Vol.35Issue(6) :34-38.DOI:10.19730/j.cnki.1008-2166.2024-06-034

基于承包商视角的电建工程索赔事件发现方法研究——以火力发电工程为例

Research on the Method of Discovering Power Construction Engineering Claims from the Perspective of Contractors——Taking Thermal Power Generation Engineering As an Example

杨凯1
扫码查看

作者信息

  • 1. 中国能源建设集团浙江火电建设有限公司,浙江 杭州 310001
  • 折叠

摘要

建设项目中发现索赔事件是开展索赔工作的前提条件.但是,随着电力建设市场竞争日趋激烈,业主先行拟定的合同条件日益苛刻;同时,由于电建市场开放较迟,承包商索赔意识不强,大多数商务人员还是习惯从合同明示可索赔条款中寻找索赔机会,不擅于通过深入项目实际研究,并分析造价理论、法律法规、政策文件、标准规范等途径和方法寻找隐形索赔机会.以上原因造成承包商索赔机会减少,给自身经济利益和企业声誉带来损失.文章结合电建工程建设管理特点,应用工程索赔管理理论,提炼总结典型案例,论述如何通过对施工过程中出现的项目特征变更、清单计价规则、重大设计变更、施工方案变更、甲供物资状态等干扰事件的深入研究分析,积极寻找发现索赔事件,从而为承包商开展索赔工作提供参考.

Abstract

Discovering claims events is a prerequisite for carrying out claims work.However,with the increasingly fierce competition in the power construction market,the contract conditions drafted by the owners in advance are becoming more stringent;at the same time,due to the late opening of the power construction market,contractors have weak awareness of claims and insufficient theoretical learning.Business personnel are accustomed to seeking claims opportunities from explicit clauses in contracts,and are not good at finding hidden claims opportunities through in-depth research and analysis of cost theory,laws and regulations,policy documents,standard specifications,and other methods.The above reasons have reduced the opportunities for contractors to claim compensation,causing losses to their own economic interests and corporate reputation.The article closely combines the characteristics of power construction project management,applies engineering claim management theory,extracts and summarizes typical practical cases,and discusses how to actively seek and discover claim events through in-depth research and analysis of interference events such as changes in project characteristics,ambiguity in list pricing,major design changes,changes in construction plans,and the status of materials provided by Party A during the construction process,in order to provide guidance for contractors to carry out claim work.

关键词

承包商/索赔机会/索赔事件/索赔方法/电建工程

Key words

Contractor/Claim opportunity/Claim event/Claim method/Power construction