内河高桩件杂货码头改造工程优化设计

Optimization Design of the Renovation Engineering for High Pile General Cargo Terminal in Inland Rivers

庞利宝 王阳
港口装卸2024,Issue(2) :64-67.DOI:10.3963/j.issn.1000-8969.2024.02.022

内河高桩件杂货码头改造工程优化设计

Optimization Design of the Renovation Engineering for High Pile General Cargo Terminal in Inland Rivers

庞利宝 1王阳2
扫码查看

作者信息

  • 1. 武汉航科物流有限公司
  • 2. 中交武汉港湾工程设计研究院有限公司
  • 折叠

摘要

针对已建的内河高桩件杂货码头上增加散货装卸功能的改造过程中,已建设施利用程度较低,对现状码头运营的影响较大、建设投入高的问题,通过对码头已有设施优化、总平面设计优化、装卸工艺优化,提升码头作业功能、环保性能和装卸效率,降低改造工程投资,缩短建设周期.该改造设计方案可为类似码头工程建设提供参考.

Abstract

In response to the renovation process of adding bulk cargo handling functions to the already built inland high pile general cargo terminal,the utilization degree of the constructed facilities is relatively low,which has a significant impact on the current terminal operation and high construction investment.By analyzing the existing facilities of the terminal,optimizing the overall layout design,and selecting handling equipment reasonably,the operational function,environmental performance,and handling efficiency of the terminal are improved,the investment in the renovation project is reduced,and the construction period is shortened.This renovation design scheme can provide reference for similar dock engineering construction.

关键词

改建工程/优化设计/平面布置/装卸设备

Key words

reconstruction engineering/optimization design/floor plan/handling equipment