Discussions on the Design Key Points of Elevated Rapid Upgrading and Transformation Project
Based on the project background of G107 east-west lake section of Wuhan Rapid Upgrading and Transformation Project,combined with the current construction conditions,the external factors that affect the implementation of the project are analyzed,and the overall design key points of the project are analyzed and studied.The profile design of the viaduct is analyzed in particular,and it is believed the passage clearance,landscape function,golden section should be considered in general,and the current situation such as parallel light rail,reserved long-term planning space and other factors should be considered in details,and at the same time the drainage problem of the viaduct should be paid attention to.
elevated expresswayupgrading and transformationprofile designintersection designviaduct types selection