首页|大断面小净距隧道爆破施工合理间距及减振措施

大断面小净距隧道爆破施工合理间距及减振措施

扫码查看
小净距隧道在爆破施工过程中存在多次扰动问题,一方面隧道周边岩土体在多次爆破扰动下发生劣化,降低围岩承载能力,另一方面爆破振动会直接对既有隧道结构产生不同程度的影响甚至损坏,如衬砌结构开裂、剥落等.因此,合理设计隧道间距以及采取必要的减振措施对于提升隧道整体安全性能以及延长隧道服役性能至关重要.为研究不同围岩级别下隧道的合理间距,以义东高速西甑山公路隧道小净距段为工程依托,采用ANSYS LS-DYNA有限元动力分析程序建立小净距隧道爆破施工三维数值模型,重点研究Ⅲ,Ⅳ,Ⅴ级围岩后行洞爆破施工下相邻先行洞振动响应规律,建立围岩级别、振速以及隧道间距内在关系式,结合衬砌结构振速限值划分合理间距,并探究减振孔在小净距隧道爆破施工中的应用,现场选取试验段开展先行洞振动监测并评价降振效果.研究表明:先行洞迎爆侧边墙位置振速值最大,以此为基础划分Ⅲ,Ⅳ,Ⅴ级围岩下隧道合理间距分别为 5.8,8.2,11.1 m,当间距小于该值时应加强监测并采取相应减振、加固措施;后行洞设置减振孔后,振速计算值、监测值相比未设置的减振率分别提高 18.7%,32.6%,二者相差不大表明减振孔降振效果明显;实际监测振速最大值为 3.49 cm/s,远小于 7 cm/s的限值,先行洞二次衬砌振速值满足安全控制要求.
Reasonable Spacing and Vibration Reduction Measure for Tunnel Blasting with Large Section and Small Clear Distance
In the tunnel blasting construction with small clear distance,the rock and soil mass around tunnel deteriorate due to disturbance of multiple blasting,and the bearing capacity of surrounding rock is reduced.At the same time,blasting vibration directly affects the existing tunnel structure to varying degrees of impact even damage,e.g.as lining structure cracking,peeling,etc.Therefore,the reasonable design of tunnel spacing and necessary vibration reduction measures are very important to improve the overall safety performance of tunnel,and to prolong the service performance of tunnel.To study the reasonable spacing of tunnel with different surrounding rock level,taking the small clear distance section of Xizengshan highway tunnel on Yiwu-Dongyang expressway as study background,ANSYS LS-DYNA finite element dynamic analysis program is adopted to establish the 3D numerical model for small clear distance tunnel blasting construction.The vibration response rule of adjacent first-excavation hole is focused under the subsequent hole blasting construction of grade Ⅲ,Ⅳ and Ⅴ surrounding rocks.The internal relations of surrounding rock level,vibration velocity,and tunnel spacing are established.The reasonable spacing is divided according to the vibration velocity limit of lining structure.The application of vibration reduction hole in blasting construction of small spacing tunnel is explored.The test section is selected to carry out the vibration monitoring of first-excavation hole,and the evaluate the vibration reduction effect.The result indicates that the vibration velocity value of side wall of blasting side of first-excavation hole is the largest.Based on this,the reasonable tunnel spacing of surrounding rock of grade Ⅲ,Ⅳ and Ⅴ is 5.8,8.2,11.1 m respectively.When the spacing is less than above values,the monitoring should be strengthened,and the corresponding vibration reduction and reinforcement measures should be taken.After the damping hole is arranged in the subsequent hole,the calculated value of vibration velocity and the monitored value increase by 18.7%and 32.6%respectively,indicating that the effect of damping hole is obvious.The maximum value of vibration velocity is 3.49 cm/s,which is far less than the limit value of 7cm/s.The vibration velocity of secondary lining of first-excavation hole meets the safety control requirements.

tunnel engineeringreasonable spacingANSYS LS-DYNA dynamic analysisstructural blasting vibration velocityon-site monitoring

林豪、郭洪雨、兰庆男、王泽樑、张志强

展开 >

浙江交投高速公路建设管理有限公司,浙江 金华 321000

浙江义东高速公路有限公司,浙江 东阳 322100

浙江数智交院科技股份有限公司,浙江 杭州 310000

西南交通大学 土木工程学院,四川 成都 610031

展开 >

隧道工程 合理间距 ANSYS LS-DYNA动力分析 结构爆破振速 现场监测

国家自然科学基金项目浙江省交通运输厅科技计划项目

523784142021-GCKY-01

2024

公路交通科技
交通运输部公路科学研究院

公路交通科技

CSTPCD北大核心
影响因子:1.007
ISSN:1002-0268
年,卷(期):2024.41(6)