首页|大藤峡水利枢纽工程土地补偿标准调整投资测算

大藤峡水利枢纽工程土地补偿标准调整投资测算

扫码查看
按照桂国土资发[2015]89号文标准(方案一)和桂国土资发[2015]89号文标准+长期补偿(方案二)两套方案分别测算大藤峡水利枢纽工程土地补偿投资,并分别与初步设计阶段土地补偿投资进行对比分析,方案一比初步设计批复投资增加92 298.92万元;方案二采取长期补偿的土地计算到2025年,采取一次性补偿的土地按桂国土资发[2015]89号文的补偿标准,测算投资比初步设计批复投资增加21452.06万元,推荐采用方案二.
Investment calculation for Datengxia Hydraulic Complex due to adjustment of land compensation standard
The land compensation investment was calculated according to two alternatives,one is the File Guiguotuzi-fa[2015]No.89(scheme I),another is the above mentioned file combined with long-term compensation(scheme II).The calculation period for the land adopting long-term compensation is until 2025.The land that adopts one-time compensation shall be compensated according to the compensation standards specified in the File Guiguotuzifa[2015]No.89.The calculation results were compared with the land compensation investment calculated at the pre-liminary design stage,with the investments of scheme I and scheme II increasing 922.9892 million yuan and 214.5206 million yuan respectively.Scheme II was recommended.

adjustment of land compensation standardinvestment calculationDatengxia Hydraulic Complex

樊现元

展开 >

广西水利电力勘测设计研究院有限责任公司,南宁 530023

土地补偿标准调整 投资测算 大藤峡水利枢纽

2024

广西水利水电
广西水利电力勘测设计研究院

广西水利水电

影响因子:0.135
ISSN:1003-1510
年,卷(期):2024.(4)