首页|某抽水蓄能电站施工总布置规划研究

某抽水蓄能电站施工总布置规划研究

扫码查看
介绍了某抽水蓄能电站的工程概况及工程地质情况.论述了该抽水蓄能电站的施工分区、场内交通、工厂设施、营地及管理设施、料源及渣场的布置设计.提出抽水蓄能电站在开展施工总布置规划时应重点关注降低工程投资、保障工程建设进度、节约工程建设用地等问题.
Study of general construction layout planning for a pumped storage power station
An introduction is made on the general information and engineering geological conditions of a pumped storage power station.The authors present the layout design of construction zoning,internal transport,factory facili-ties,campsite and management facilities,material sources and disposal yards.It is pointed out that the general con-struction layout planning of pumped storage power stations should focus on reducing project investment,ensuring construction progress,and saving construction land etc.

pumped storage power stationgeneral construction layoutconstruction landproject investment

田明俊、胡玉贵

展开 >

中国能源建设集团广西电力设计研究院有限公司,南宁 530007

抽水蓄能电站 施工总布置 建设用地 工程投资

2024

广西水利水电
广西水利电力勘测设计研究院

广西水利水电

影响因子:0.135
ISSN:1003-1510
年,卷(期):2024.(6)