以柳州火车站的高架层悬臂结构为工程背景,通过有限元法分析了施工阶段临时支撑回顶与否,临时支撑和临时支架拆除与否等不同工况的内力、变形、裂缝等结果,确定了悬臂板上部设置临时支架,下部设置临时支撑进行回顶,后期拆除临时支撑和临时支架的施工方案.同时为了保证施工的顺利进行,利用静力水准仪进行了挠度的监测,通过监测发现变形符合规范要求,保证了施工安全.
Construction Method Research and Monitoring of Cantilever Structure of Liuzhou railway station
Considering Liuzhou Railway Station elevated floor's cantilever structure,it has been ana-lyzed by Finite element method that is the internal force,deformation,cracks under different working conditions whether the temporary support is returned to the top and the temporary sup-ports are removed during the construction stage are analyzed.It is determined that is It is relative-ly reasonable method that temporary support should be installed on the upper part of the cantile-ver plate,and setting on the lower part for returning to the top,and removing temporary support and temporary support in the later stage.In order to ensure safe construction,a static level was used to monitor the deflection.Through monitoring,it was found that the deformation met the regulatory requirements,ensuring construction safety.

construction monitoringdeflectionconstruction conditionsstatic leveling instrument

孙焰、伍旌红

展开 >

中国铁路南宁局集团有限公司柳州铁路工程建设指挥部,柳州市 545000

施工监测 挠度 施工工况 静力水准仪

中国铁路南宁局集团有限公司科技项目

建22-13

2024

河北建筑工程学院学报
河北建筑工程学院

河北建筑工程学院学报

影响因子:0.502
ISSN:1008-4185
年,卷(期):2024.42(2)