首页|220m级高土质边坡快速施工关键技术研究

220m级高土质边坡快速施工关键技术研究

扫码查看
海南迈湾水利枢纽工程主坝土质边坡高 220 m,支护形式复杂.针对高土质边坡快速施工难点,本研究提出了多个小台阶多个支护面同步施工工法,通过试验优化了锚索施工工艺和锚墩模板施工工艺,形成了一套适用于热带季风气候高土质边坡锚杆、锚索施工工艺,提高了边坡开挖支护施工质量及进度,边坡开挖支护完工时间较总进度计划提前近2 个月.该研究可为今后高土边坡快速施工提供参考.
Key Technologies for Rapid Construction of 220-meter High Soil Slopes
The soil slopes at the abutments of the main dam in Maiwan Water Conservancy Project in Hainan Province are of 220 meter high and with complex support structures.To address the challenges in rapid construction of the high soil slopes,a synchronous construction method with multiple small steps and support surfaces is proposed.The construc-tion processes of the anchor cables and the anchor piers are optimized with experiments,and a set of construction tech-niques of anchor cables and anchor piers suitable for high soil slopes in tropical monsoon climate is obtained.The tech-niques improve the quality and progress of the slope excavation and support construction.The completion time of the slope excavation and support construction is nearly 2 months earlier than the overall schedule.The research provides use-ful reference for the rapid construction of high soil slopes in the future.

220-meter levelhigh soil sloperapid constructionkey technologywater conservancy projects

赵华勇

展开 >

中国葛洲坝集团第一工程有限公司,湖北 宜昌 443002

220m级 高土质边坡 快速施工 关键技术 水利枢纽

2024

水电与新能源
湖北省水力发电工程学会 湖北能源集团股份有限公司

水电与新能源

影响因子:0.301
ISSN:1671-3354
年,卷(期):2024.38(12)