水利水电工程基坑排水量大小关系到抽排水设备选型、配置及布置.针对碾盘山水利水电枢纽工程二期枯期围堰基坑排水问题,计算分析了初期排水量与经常性排水量,提出了水泵选型和主管布置方案.实践表明水泵选型、排水能力满足工程施工需要.研究可供类似工程基坑抽排水计算及施工参考.
Drainage Calculation for the Foundation Pit of the Second Stage Cofferdam in Nianpanshan Water Conservancy Project
The drainage volume of foundation pits in water conservancy and hydropower projects affects the selection,configuration and layout of pumping equipment.Regarding the drainage problem of the foundation pit of the second stage dry-season cofferdam in Nianpanshan Water Conservancy Project,the initial and regular drainage volumes are calculated and analyzed,and a pump selection and main pipe layout scheme is proposed.Practice shows that the drainage capacity of the selected pump meets the construction requirements.The research provides useful reference for the drainage calcu-lation and construction of foundation pits in similar projects.

Nianpanshan Projectfoundation pit drainagetheoretical calculationpump selection

马辉文

展开 >

中国水电基础局有限公司,天津 301700

碾盘山工程 基坑排水 理论计算 水泵选型

2024

水电与新能源
湖北省水力发电工程学会 湖北能源集团股份有限公司

水电与新能源

影响因子:0.301
ISSN:1671-3354
年,卷(期):2024.38(12)