介绍了铁塔经济性高度优化原理及大跨越线路成本建模的方法.通过建立数学模型,以总费用为目标函数,以载流量校验、电压降校验以及电晕校验等形成约束条件,以导线型号、导线类型、铁塔类型组成设计空间,计算出最优的组合.通过具体的实例来分析,得到了经济性优化跨越塔塔高及导线.
Research on economical efficiency optimization of large crossing high power line and tower height
Our transmission line project is in full swing,but studies of large span economical optimization very few,be badly in need of theoretical guidance.To this end,this paper introduces in detail the tower economy highly optimized principle and method of large cross line of cost modeling.By establishing a mathematical model,with the total cost as the objective function and with current carrying capacity check、voltage drop check and corona checksum formed to constraints and with the wire type,tower type composition of the design space to calculate the optimal combination.Finally,through the analysis of specific examples to get the economical efficiency optimization of large crossing tower height and large crossing power line type.This topic can offer tower choice and conductor selection optimization opinions to large cross line construction,guidelines for the large cross line construction play a bigger role.

large crossing power linetower heightlarge cross line costeconomical efficiency optimization

阴酉龙、项川、苏静、吴世平

展开 >

三峡大学电气与新能源学院,湖北宜昌443002

宜昌供电公司经济技术研究所,湖北宜昌443000

商丘虞城供电有限责任公司,河南商丘476000

国网安徽和县供电有限责任公司,安徽马鞍山238201

展开 >

大跨越导线 塔高 大跨越线路成本 经济性优化

2014

华东电力
华东电力试验研究院有限公司

华东电力

CSTPCD
影响因子:0.551
ISSN:1001-9529
年,卷(期):2014.42(7)
  • 1
  • 4