核动力工程2024,Vol.45Issue(2) :203-206.DOI:10.13832/j.jnpe.2024.02.0203

一回路注锌技术应用及注锌加药设备设计

Primary Zinc Injection Technology Application and Zinc Injection and Dosing Equipment Design

邹伟 林根仙 孙云
核动力工程2024,Vol.45Issue(2) :203-206.DOI:10.13832/j.jnpe.2024.02.0203

一回路注锌技术应用及注锌加药设备设计

Primary Zinc Injection Technology Application and Zinc Injection and Dosing Equipment Design

邹伟 1林根仙 1孙云1
扫码查看

作者信息

  • 1. 苏州热工研究院有限公司,江苏苏州,215000;国家核电厂安全及可靠性工程技术研究中心,江苏苏州,215000
  • 折叠

摘要

一回路注锌技术的应用使得一回路设备表面生成的氧化膜更加稳定,起到降低机组集体剂量的作用.通过分析注锌对机组影响,结合国内某在运压水堆机组注锌目标浓度和现场设备存放条件,设计一套注锌加药设备,明确其设计方案、设备部件参数和工作流程.该设备由溶液混合单元、过滤单元、加药单元及控制单元组成,实现机组运行期间添加醋酸锌和大修期间添加双氧水两种功能应用.

Abstract

The application of primary zinc injection technology makes the oxide film generated on the surface of the primary equipment more stable and plays a role in reducing the collective dose of the unit.By analyzing the effect of zinc injection on the unit,and combining the target concentration of zinc injection in a domestic PWR unit and the conditions of the on-site equipment,a set of zinc injection and dosing equipment is designed,and its design scheme,equipment component parameters and working flow are defined.The equipment is composed of a solution mixing unit,a filtration unit,a dosing unit and a control unit,which can be used to add zinc acetate during operation and hydrogen peroxide during overhaul.

关键词

压水堆/一回路注锌/加药设备

Key words

Pressurized water reactor/Primary zinc injection/Dosing equipment