首页|多煤层复合采动顶底板裂隙带发育规律研究

多煤层复合采动顶底板裂隙带发育规律研究

扫码查看
基于友众煤矿多煤层复合采动顶底板裂隙发育情况,分别采用理论计算、数值模拟和钻孔实测等方法进行研究,计算统计出150202工作面顶板垮落带发育高度分别为40.11~63.09m、50.2 m、54~57 m,3种方式结果变化范围基本一致.结合矿井地质条件和研究结果可知,15号下煤层采动裂隙带在无构造区域内不会导通上覆3号、6号含水层,在贯穿性断层或陷落柱赋存区域内存在联通导水的可能性.因此,煤矿制定"物探先行、钻探验证、查清构造、上防下采"的防治水原则,为相关类型矿井生产提供依据.
Study on the development law of fracture zone in roof and floor of multi-coal seam composite mining
Based on the fracture development of roof and floor of multi-coal seam composite mining in Youzhong Mine,theoretical calculation,numerical simulation and drilling measurement were used to study.The development height of roof caving zone in No.150202 Face was 40.11~63.09 m,50.2 m and 54~57 m respectively,and the variation range of the three methods was basically the same.Combined with the geological conditions and research results of the mine,it could be concluded that the mining fracture zone of No.15 lower coal seam would not conduct the overlying No.3 and No.6 aquifers in the non-structural area,and there was a possibility of water conduction in the occurrence area of penetrating faults or collapse columns.Therefore,coal mine formulated the water prevention and control principle of'geophysical prospecting first,drilling verification,structure investigation,upper prevention and lower mining',which provided the basis for the production of related types of mines.

multiple coal seamswater conduction fracturesdrilling measurementwater prevention and controlcomposite roofstress concentration

刘振坡、袁鹏

展开 >

山东新矿集团华源公司友众煤业,山西晋中 045400

多煤层 导水裂隙 钻孔实测 防治水 复合顶板 应力集中

2024

煤炭与化工
河北省化学工业研究院

煤炭与化工

影响因子:0.246
ISSN:2095-5979
年,卷(期):2024.47(4)