水库堤坝劈裂灌浆防渗加固施工技术

扫码查看
为控制水库堤坝渗流及裂缝,提升水库堤坝运行的安全性和稳定性,以瑞金市日东乡湖陂村的日东水库为例,在概述水库渗漏现状及地质条件的基础上,提出劈裂灌浆防渗加固方案,并从岸坡布孔、分序钻灌、封孔、坝面处理等方面对施工过程展开分析。应用后水库堤坝渗漏及裂缝均得到较好处治,也为水库稳定运行提供了保证。
Anti-seepage and Reinforcement Construction Technology of Fracture Grouting of Reservoir Embankments
In order to control the seepage and cracks of the reservoir dam,improve the safety and stability of the operation of the reservoir dam,taking the Ridong Reservoir in Hupi Village,Ridong Township,Ruijin City as an example,based on an overview of the current situation of reservoir leakage and geological conditions,a anti-seepage reinforcement plan of fracture grouting is proposed,and the construction process is analyzed from the aspects of bank slope hole layout,sequential drilling and grouting,hole sealing,and dam surface treatment.After application,the leakage and cracks of the reservoir dam have been well treated,which also provides a guarantee for the stable operation of the reservoir.

reservoir embankmentfracture groutinganti seepage reinforcementconstruction

李长勇

展开 >

瑞金市水利工程技术保障中心,江西 瑞金 342500

水库堤坝 劈裂灌浆 防渗加固 施工

2024

河南水利与南水北调
河南省水利厅

河南水利与南水北调

影响因子:0.382
ISSN:1673-8853
年,卷(期):2024.53(7)