Progress Management of LNG Storage Tank Pile Foundation Project under EPC Mode
As the first part of the critical path of the project,the completion time of LNG storage tank pile foundation project directly affects the civil construction and installation construction,causing the delay of works,so the progress management of the pile foundation project is of vital importance.This paper introduces the progress management strategies and methods in the preparation and construction phase of the pile foundation project,and takes an LNG project in Zhejiang as an example to analyze the main factors affecting the progress of the pile foundation construction as well as the management methods by using the"5M1E"method,which is aimed at providing references for the progress management of the pile foundation project of the subsequent project for general contractor.
grouted pile constructionpile foundation projectLNG storage tank