600 MW亚临界机组锅炉炉墙振动原因分析及治理

扫码查看
针对京隆发电2号机组投产以来锅炉左侧炉墙一直存在较大振动的状况,采用锅炉内部结构全尺寸1:1建模对炉内流场进行分析.通过热态测试、冷态检查、计算流体动力学(CFD)流场分析、模态分析等方法,得出炉墙振动的主要原因是锅炉内部存在不稳定烟气流.根据振动原因对锅炉内、外部结构进行了优化,炉墙振动烈度较治理前下降77%~88%,提高了锅炉运行的安全性.
Analysis and treatment of boiler wall vibration of 600 MW subcritical unit
Since the Jinglong No.2 power generation unit was put into operation,there has been a large vibration on the left side of the boiler wall,and the flow field in the furnace was analyzed by using the full-size 1:1 modeling of the boiler internal structure.Through the hot state test,cold state check,CFD(computational fluid dynamics)flow field analysis,modal analysis and other methods,the main reason for the vibration of the furnace wall was the existence of unstable smoke airflow in the boiler.According to the causes of vibration,the internal and external structure of the boiler is optimized,and the vibration intensity of the furnace wall is reduced by 77%~88%,which further improves the safety of the boiler operation.

boilervibration of furnace wallflow field optimizationmodelingstructural optimization

王荣、韩建衡、贾志军、王耀

展开 >

内蒙古京隆发电有限责任公司,内蒙古丰镇 012100

内蒙古机电职业技术学院,呼和浩特 010070

新疆油田公司应急抢险救援中心,新疆克拉玛依 834000

锅炉 炉墙振动 流场优化 建模 结构优化

2024

黑龙江电力
黑龙江省电机工程学会 黑龙江省电力科学研究院

黑龙江电力

影响因子:0.359
ISSN:1002-1663
年,卷(期):2024.46(1)