预应力混凝土挂篮悬臂浇筑施工技术研究

扫码查看
挂篮悬浇施工技术正逐步的成熟完善,目前铁路工程跨路、跨河施工中经常采用挂篮悬臂浇筑施工工法.在介绍常见挂篮形式的基础上,以石衡沧港城际铁路阜城跨281省道特大桥(60+100+60)m连续梁为例,在挂篮施工的前期准备工作、挂篮的制作及安装、挂篮的预压、混凝土浇筑、预应力施工、连续梁合龙、线性监控、挂篮的行走和拆除等方面探讨桥梁悬浇施工工艺.
Research on Construction Technology of Cantilever Pouring of Prestressed Concrete Hanging Basket
Hanging basket hanging casting construction technology is gradually mature and perfect,at present,hanging basket cantilever casting construction method is often used in railway construction across roads and rivers.On the basis of introducing the common forms of hanging baskets,taking the continuous beam of the(60+100+60)m bridge across 281 Provincial Road of Shiheng Cangang Port Intercity Railway Fucheng as an example,The construction technology of bridge suspension casting is discussed in the aspects of preliminary preparation,quality supervision system,production and installation of hanging basket,preloading of hanging basket,concrete pouring,prestress construction,continuous beam closing,linear monitoring,walking and dismantling of hanging basket,etc.

hanging basketcantilever pouringconstruction technology

李冰

展开 >

中交一航局第一工程有限公司,天津

挂篮 悬臂浇筑 施工技术

2024

科学技术创新
黑龙江省科普事业中心

科学技术创新

影响因子:0.842
ISSN:1673-1328
年,卷(期):2024.(8)
  • 3