首页|西北地区电网不良地质处理方案及造价分析

西北地区电网不良地质处理方案及造价分析

扫码查看
我国西北地域幅员辽阔,各种不良地质条件分布广泛,严重影响了电网基础设施建设进程.本文首先分析统计了西北各地区各类不良地质条件分布情况;然后,针对湿陷性、液化、盐渍土这三种典型不良地质条件提出了多种地基处理方案;最后,以通用设计A1-1方案为例研究了不同地基处理方案的适用性和经济性,计算出了各类不同深度不良地基的处理费用.可为电网类似工程提供可借鉴的技术建议.
Solution and Cost Analysis for Handling Unfavorable Geological Conditions in Northwest Power Grid
The northwest of China has a vast territory and various unfavorable geological conditions are wide-ly distributed,seriously affecting the construction process of power grid infrastructure.This article first ana-lyzes and calculates the distribution of various unfavorable geological conditions in various regions of the northwest of China.Then,a foundation treatment plan is proposed for three typical unfavorable geological con-ditions:collapsibility,liquefaction and saline soil.Finally,the applicability and economy of different foundation treatment schemes are studied by taking the universal design A1-1 scheme as an example,and the treatment costs of various kinds of bad foundations with different depths are calculated.This article can provide techni-cal suggestions for similar projects in the power grid.

unfavorable geological conditionscollapsibilityliquefactionsaline soil

王永华、李强、李云山、陈露锋、莫海涛、郑敏

展开 >

国网新疆电力有限公司经济技术研究院,乌鲁木齐 830001

上海大学 机电工程与自动化学院,上海 200444

不良地质条件 湿陷性 液化 盐渍土

2024

湖南工程学院学报(自然科学版)
湖南工程学院

湖南工程学院学报(自然科学版)

影响因子:0.265
ISSN:1671-119X
年,卷(期):2024.34(3)