首页|水电工程石方洞挖数码电子雷管联网方案及耗量分析方法研究

水电工程石方洞挖数码电子雷管联网方案及耗量分析方法研究

扫码查看
自 2021 年在水电工程爆破开挖中强制推行应用数码电子雷管后,关于数码电子雷管的爆破联网设计方案、实际消耗量、成本分析等研究尚处于空白阶段.笔者从数码电子雷管与非电毫秒雷管爆破联网设计方案对比分析入手,研究两者的爆破联网方式差异,理论推导两者耗量调整系数.同时采用无约束支持向量机模型构建雷管耗量与岩石级别、开挖断面的函数关系,计算数码电子雷管替换非电毫秒雷管后的耗量调整系数,并采用单一变量试验验证计算数据的准确性.结果表明,实测数据结果与理论推导结果、数学模型分析结果保持一致,证明两种研究方法的可靠性.
Networking Scheme and Consumption Analysis Method of Digital Electronic Detonator for Rock Excavation in Hydropower Project
Since the mandatory application of digital electronic detonators in the blasting excavation of hydropower projects in 2021,the research on the blasting networking design scheme,actual consumption and cost analysis of digital electronic detonators is still in the blank stage.The authors start with the comparative analysis of the design scheme of digital electronic detonator and non-electric millisecond detonator blasting network,study the difference of blasting network mode between the two detonators,and theoretically derive the consumption adjustment coefficient of the two detonators.At the same time,the unconstrained support vector machine model is used to construct the functional relationship between detonator consumption and rock grade and excavation section.The consumption adjustment coefficient of digital electronic detonator after replacing non-electric millisecond detonator is calculated,and the accuracy of the calculated data is verified by single variable test.The results show that the measured data results are consistent with the theoretical derivation results and the mathematical model analysis results,which proves the reliability of the two research methods.

digital electronic detonatornon-electric millisecond detonatorexplosive networkingunconstrained support vector machineadjustment coefficient

刘春高、马赫、唐永发、乔天霞

展开 >

水电水利规划设计总院,北京 100120

国网新源集团有限公司,北京 100052

中国电建集团成都勘测设计研究院有限公司,四川 成都 610072

国网新源控股有限公司抽水蓄能技术经济研究院,北京 100053

展开 >

数码电子雷管 非电毫秒雷管 爆破联网 无约束支持向量机 调整系数

2024

红水河
广西水力发电工程学会 广西电力工业勘察设计研究院

红水河

影响因子:0.132
ISSN:1001-408X
年,卷(期):2024.43(3)