广西抽水蓄能电站建设征地实物指标及征地移民补偿费用研究分析

Research and Analysis on Land Acquisition Physical Index and Resettlement Compensation Cost for Construction of Pumped Storage Power Station in Guangxi

叶发勇
红水河2024,Vol.43Issue(5) :100-104.DOI:10.3969/j.issn.1001-408X.2024.05.019

广西抽水蓄能电站建设征地实物指标及征地移民补偿费用研究分析

Research and Analysis on Land Acquisition Physical Index and Resettlement Compensation Cost for Construction of Pumped Storage Power Station in Guangxi

叶发勇1
扫码查看

作者信息

  • 1. 中国能源建设集团广西电力设计研究院有限公司,广西 南宁 530007
  • 折叠

摘要

随着新能源的高速发展,广西抽水蓄能电站也将进入规模化开发建设阶段.笔者通过对广西已建或在建、拟建的 10 座抽水蓄能电站建设征地实物指标及征地移民补偿费用进行研究分析,归纳出广西区内抽水蓄能电站建设征地实物指标和征地移民补偿费用的主要特征,为今后开发建设区内其他类似项目提供参考借鉴.

Abstract

With the rapid development of new energy,pumped storage power stations in Guangxi will also enter the stage of large-scale development and construction.Based on the research and analysis of the physical index of land acquisition and the compensation cost of land acquisition and resettlement for the construction of 10 pumped storage power stations that have been built or under construction or proposed in Guangxi,the author summarizes the main characteristics of the physical index of land acquisition and the compensation cost of land acquisition and resettlement for the construction of pumped storage power stations in Guangxi,and provides reference for the development and construction of other similar projects in the region in the future.

关键词

建设征地/实物指标/补偿费用/抽水蓄能电站/广西

Key words

land acquisition for construction/physical index/compensation cost/pumped storage power station/Guangxi