通古孜布隆水库大坝温控的重点是高温时节混凝土浇筑温度控制和冬季保温问题,参考相关工程经验,提出夏季采用通水冷却、冬季采用聚氨酯作为保温层的混凝土浇筑温控措施。为评价温控措施的可行性,以 4号非溢流坝段为例,通过利用三维有限元软件进行混凝土浇筑温控仿真模拟计算分析。结果表明:施工期与运行期的温控措施有效,通水冷却可以降低温度 3℃~6℃;施工期和运行期的最大温度应力均不超过混凝土允许应力,满足规范要求。
Temperature Control Simulation Calculation of Tongguzibulong Reservoir Dam
The focus of temperature control of Tongguzibulong Reservoir dam is the temperature control of concrete pouring in high temperature season and heat preservation in winter.Referring to relevant engineering experience,the temperature control measures of concrete pouring with water cooling in summer and polyurethane as insulation layer in winter are put forward.In order to evaluate the feasibility of temperature control measures,taking No.4 non-overflow dam section as an example,the simulation calculation and analysis of concrete pouring temperature control are carried out by using three-dimensional finite element software.The results show that the temperature control measures during the construction period and the operation period are effective,and the water cooling can reduce the temperature by 3℃~6℃;The maximum temperature stress during the construction period and the operation period does not exceed the allowable stress of concrete,which meets the requirements of the specification.

temperature fieldtemperature control measuresthree-dimensional finite element analysissimulation calculationTongguzibulong Reservoir

马永磊、江晨芳

展开 >

新疆水利水电勘测设计研究院有限责任公司,新疆 乌鲁木齐 830099

中国水利水电科学研究院,北京 100083

温度场 温控措施 三维有限元分析 仿真计算 通古孜布隆水库

2024

红水河
广西水力发电工程学会 广西电力工业勘察设计研究院

红水河

影响因子:0.132
ISSN:1001-408X
年,卷(期):2024.43(6)