吉林电力2024,Vol.52Issue(1) :35-39.

一种双回路220kV线路反向π接钢管杆方案的研究

Research on the Reverse π Connected Steel Pipe Pole Scheme for Double Circuit 220 kV Transmission Lines

曹彦斌 刘洋 于志红
吉林电力2024,Vol.52Issue(1) :35-39.

一种双回路220kV线路反向π接钢管杆方案的研究

Research on the Reverse π Connected Steel Pipe Pole Scheme for Double Circuit 220 kV Transmission Lines

曹彦斌 1刘洋 1于志红1
扫码查看

作者信息

  • 1. 中国电建集团吉林省电力勘测设计院有限公司,长春 130022
  • 折叠

摘要

针对在电网工程规划、设计和建设中220 kV架空输电线路的π接越来越难的问题,设计了一种接线简单、占地少、施工停电时间短、便于施工和维护的π接钢管杆方案,并与常规π接方案对比,在某220 kV线路工程的实际应用中,验证了所提方案的可行性和有效性.

Abstract

In response to the increasingly difficult problem of π connection of 220 kV overhead transmission lines in power grid engineering planning,this paper proposes a π connection steel pipe pole scheme with simple wiring,less land occupation,short construction power outage time,and easy construction and maintenance.Compared with conventional π connection schemes,the feasibility and effectiveness of the proposed scheme have been verified in the practical application of a certain 220 kV line project.

关键词

架空输电线路/220/kV/钢管杆

Key words

overhead transmission line/220 kV/steel pipe pole