摘要

以某项目工程设计采购施工(EPC)总承包工程大基坑快速施工为例,研究如何快速施工超大基坑,提出大型基坑开挖前塔吊预安装施工技术、装配式综合排水施工技术、基坑分层分区的总体组织流水施工技术、基坑预加固施工技术,将缩短传统基坑施工的周期和节约投资.

Abstract

Taking the rapid construction of large foundation pit of a project engineering design,procurement and construction(EPC)general contracting project as an example,this paper analyzes and studies how to quickly construct a large foundation pit,and proposes the pre-installation construction technology of tower crane before excavation of large foundation pit,the construction technology of prefabricated comprehensive drainage,the overall organization flow construction technology of foundation pit layered partitioning,and the construction technology of foundation pit pre-reinforcement,which will shorten the cycle of traditional foundation pit construction and save investment.

关键词

超大基坑/塔吊预安装/装配式排水/分区施工/基坑预加固

Key words

super-large foundation pit/tower crane pre-installation/prefabricated drainage/zoning construction/foundation pit pre-reinforcement

引用本文复制引用

出版年

2024
江苏建材
江苏省建材工业协会

江苏建材

影响因子:0.257
ISSN:1004-5538
段落导航相关论文