Analysis and Solution Measures for Dewatering of Foundation Pit in Subway Stations
During the excavation process of the subway station foundation pit,due to the failure of the dewatering well,it cannot provide good dewatering effect,resulting in the excavation process of the foundation pit and soaking after reaching the bottom,seriously affecting the normal construction progress of the station and the bearing capacity of the substrate foundation.A deep analysis was conducted on the quality problem of foundation pit dewatering in Shenzhen subway station,and effective treatment measures were proposed.The ineffective dewatering well was revived and achieved good dewatering effect.This measure solved the problem of base bubble groove and ensured the normal progress of subsequent construction.
subway stationconstruction of dewatering wellsfoundation pit dewatering