随着顶管技术在地下工程建设中的广泛应用,不可避免会穿越临近既有建(构)筑物.文章以广州某电力隧道顶管施工上跨既有城际铁路隧道为背景,采用岩土专业分析软件MIDAS GTS NX,建立三维有限元计算模型,采用位移法控制实现了工作井开挖及顶管施工过程模拟,分析了电力隧道顶管施工对既有城际铁路隧道管片、无砟轨道受力变形的影响,以期对类似工程提供参考.
Safety Impact Assessment of Power Tunnel Pipe Jacking Construction Overcrossing Existing Intercity Railway Tunnel
With the extensive application of pipe jacking in underground engineering construction,it is inevitable to cross the adjacent existing building structures.In this paper,based on the pipe jacking construction of a power tunnel overcrossing existing intercity railway tunnel in Guangzhou,a three-dimensional finite element calculation model is established by using MIDAS GTS NX of geotechnical professional analysis software.Base on the numerical simulation of working well excavation and pipe jacking construction by using displacement method control,the paper analyses the influence of power tunnel pipe jacking construction on the stress and deformation of existing intercity tunnel,hoping to provide reference for similar projects.

pipe jacking constructionintercity tunnelnumerical simulationMIDAS GTS NX

毛淑欣、徐金刚

展开 >

苏交科集团股份有限公司,江苏南京 210000

江苏省地质工程勘察院,江苏南京 210000

顶管施工 城际隧道 数值模拟 MIDAS GTS NX

2024

江苏建筑
江苏省土木建筑学会,江苏省建筑科学研究院有限公司

江苏建筑

影响因子:0.395
ISSN:1005-6270
年,卷(期):2024.(2)