首页|嵌岩桩承载力不足原因分析及补强措施研究

嵌岩桩承载力不足原因分析及补强措施研究

扫码查看
冲孔灌注桩作为一种比较常见的基础形式被广泛应用于高层建筑中,但由于其施工工艺的特点和人员技术水平的差异,经常出现定岩困难、沉渣厚度超标、桩身离析等质量问题,导致基桩承载力不满足设计要求,因此研究承载力不足桩基础补强措施具有重要意义.文中结合某工程实例,对嵌岩桩承载力不足的原因进行分析,并根据工程地质勘察报告及静载、钻芯法、低应变法的检测报告,分析了嵌岩冲孔灌注桩承载力未达到设计要求的原因,并针对性提出了相应的补强措施,有效解决了嵌岩桩承载力不足的问题.
Analysis of the Reasons for Insufficient Bearing Capacity of a Rock Socketed Pile and Research on Reinforcement Measures
In current high-rise building projects,punched cast-in-place piles are widely used as a common form of foundation.However,due to the characteristics of their construction technology and the differences in the technical level of personnel,quality problems such as difficulty in rock fixation,excessive sediment thickness,and pile body segregation often occur,resulting in the problem of insufficient bearing capacity of foundation piles not meeting design requirements.Therefore,studying reinforcement measures for pile foundations with insufficient bearing ca-pacity has practical guiding significance.This article analyzes and studies the reasons for the insufficient bearing capacity of rock socketed piles based on a project example in Zhangzhou City,According to the engineering geological survey report and the testing reports of static load,core drilling method,and low strain method,the reasons for the failure of rock socketed punched cast-in-place piles to meet the design require-ments are analyzed,and corresponding reinforcement measures are proposed to effectively solve the problem of insufficient bearing capacity of rock socketed piles.

Embedded rock pilesFoundation pile core drilling methodBearing capacityReinforcement measures

周小明

展开 >

漳州台商投资区建设工程质量安全站,福建 漳州 363107

嵌岩桩 基桩钻芯法 承载力 补强措施

2024

江西建材
江西省建材科研设计院

江西建材

影响因子:2.247
ISSN:1006-2890
年,卷(期):2024.(9)