随着轨道交通的建设,盾构区间废弃桥梁桩基拔除的工程日趋增多,而老桩拔除施工会对周边环境产生较大的变形影响.因此,拔桩施工必须对影响范围内的管线做到有效控制及保护.文中以拔桩施工时邻近的地下燃气管线为研究对象,以宁波市轨道交通7 号线土建工程TJ7022 标段湾头大桥2 号楼梯拆复建桩基拔除工程为依托,采用有限元软件MIDAS GTS NX,建立软土地区钢套筒拔桩施工对城市地下管线影响的三维有限元模型.结果表明,桩基拔出施工对邻近地下燃气管线的影响主要表现为竖向沉降;将管道上方土体进行开挖换填为细砂后,各施工步管线沉降变形均有所减小,相较于未换填工况最大竖向沉降减小约 19%,减小变形效果较明显.该计算结果可为软土地区拔桩施工对邻近管线保护提供参考.
Numerical Simulation Analysis on the Influence of Pile Pulling Construction on Existing Underground Gas Pipelines in Soft Soil Areas
In recent years,with the construction of rail transit,there has been an increasing number of projects to remove abandoned bridge pile foundations in shield tunneling sections,and the removal of old piles during construction can have a significant deformation impact on the surrounding environment.Therefore,it is necessary to effectively control and protect the pipelines within the affected area during pile pulling construction.The research object of this article is the proximity of underground gas pipelines during pile pulling construction.Based on the demolition and reconstruction of the pile foundation for the 2nd staircase of the Wantou Bridge in the civil engineering project of Ningbo Metro Line 7 TJ7022 section,a three-dimensional finite element model of the impact of steel sleeve pile pulling construction on urban underground pipelines in soft soil areas is established using the finite element software MIDAS GTS NX.The calculation results indicate that the impact of pile foundation extraction construction on adjacent underground gas pipelines is mainly manifested as vertical settlement.After excavating and replacing the soil above the pipeline with fine sand,the settlement and deformation of the pipeline in each construction step have decreased,with a maximum vertical settlement reduction of about 19%compared to the non replacement condition,and the effect of reducing deformation is more obvious.The calculation results can provide reference significance for the protection of adjacent pipelines during pile pulling construc-tion in soft soil areas.

Soft soilPulling out pilesNumerical analysisUnderground pipelines

赵华、杨新应、路培波、蒋阳阳

展开 >

中铁十六局集团第三工程有限公司,浙江 湖州 313000

宁波市轨道交通集团有限公司地产开发分公司,浙江 宁波 315000

宁波市轨道交通集团有限公司建设分公司,浙江 宁波 315000

软土 拔桩 数值分析 地下管线

2024

江西建材
江西省建材科研设计院

江西建材

影响因子:2.247
ISSN:1006-2890
年,卷(期):2024.(10)