土压平衡盾构机长期停机风险预防技术措施
Technical Measures for Long Term Shutdown Risk Prevention of Earth Pressure Balance Shield Machine
肖志强1
作者信息
- 1. 江苏中车城市发展有限公司,江苏 无锡 214000
- 折叠
摘要
为确保盾构机在长期停机期间设备设施及结构的安全,实现顺利复推,安全完成盾构掘进任务,文中通过对盾构停机期间结构、设备设施存在的安全风险进行分析研究,并采取有效预防措施,证明了该措施的有效性,为类似项目提供了借鉴,进一步推动盾构机施工技术的发展.
Abstract
In order to ensure the safety of equipment,facilities,and structures during long-term shutdown of shield tunneling machines,a-chieve smooth re pushing,and safely complete shield tunneling tasks,this article analyzes and studies the safety risks of structures and equip-ment facilities during shield tunneling shutdown,and takes effective preventive measures to demonstrate the effectiveness of this measure,pro-viding reference for similar projects and further promoting the development of shield tunneling machine construction technology.
关键词
盾构机/盾构法/停机风险Key words
Shield tunneling machine/Shield tunneling method/Shutdown risk引用本文复制引用
出版年
2024