上跨高速公路匝道桥利用模块车拆除方案研究

扫码查看
文中以沪武高速董浜枢纽M匝道拆除工程为研究对象,提出了一种针对上跨既有高速主线预应力连续箱梁匝道桥利用自行式液压模块车(SPMT)的拆除方法,基于"SPMT"驮运设备,通过布设相应的支撑系统,实现跨沪武高速主线M匝道桥的快速拆除,有效解决了跨沪武高速主线匝道桥拆除施工难度大的问题,比计划用时提前2h,整个拆桥过程安全可控,证明利用SPMT模块车拆桥是正确且合理的选择.
Study on the Removal Scheme of Modular Vehicle for On-Ramp Bridge of Overpass Expressway
Taking the removal project of M ramp in Dongbang Junction of Shanghai-Wu Expressway as the object,a self-propelled hydraulic module vehicle(SPMT)was proposed for the removal of prestressed continuous box girder ramp bridge of the existing high-speed main line across the upper span.Based on the"SPMT"pack equipment,the M-ramp bridge of the main line across the Shanghai-Wu Expressway was quickly removed by laying the corresponding support system.It effectively solved the problem that the on-ramp bridge removal construction of the main line of the cross-Hu Wu high-speed was difficult,2 hours ahead of the planned time,and the whole bridge removal process was safe and controllable,which proved that the use of SPMT module to remove the bridge is a correct and reasonable choice.

Upper span existing highway"Bridge on bridge"Demolish the bridgeSPMT module car

杨林

展开 >

徐州市公路工程总公司,江苏 徐州 221009

上跨既有高速 "桥上桥" 拆桥 SPMT模块车