首页|高铁预制箱梁桁架式收面装置快速施工技术研究

高铁预制箱梁桁架式收面装置快速施工技术研究

扫码查看
随着国内工程施工水平的不断发展,高速铁路箱梁预制施工技术及施工组织已基本成熟,宜兴铁路夷陵制梁场通过对制梁工序进行深入研究分析,研究了桁架式收面装置预制箱梁快速施工技术。该技术满足预制箱梁收面要求,所需人工少,与传统收面工艺相比,本收面装置设备轻便,智能化程度高,能实现减员、提高功效、降低劳动强度和施工成本最节约的目的。从施工技术上进行了创新,在宜兴铁路夷陵制梁场得到了推广应用,也给其它类似大中型制梁场提供了有力的技术支持和借鉴。
Research on Rapid Construction Technology of Prefabricated Box Girder Truss Type Surface Acceptance Device for High-speed Rail
With the continuous development of domestic engineering construction level,the precast construction technology and construction organization of high-speed railway box girder have been basically mature.Through the in-depth research and analysis of the beam making process,the rapid construction technology of the precast box girder with trussed surface drawing device has been studied in Yixing railway Yiling beam making yard.The technology meets the requirements of prefabricated box girder surface,and requires less labor.Compared with the traditional surface process,the surface device is light and intelligent,and can achieve the purpose of reducing staff,improving efficiency and reducing labor intensity and construction cost.It innovates in the construction technology,and has been popularized and applied in Yiling beam making yard of Yixing Railway,and also provides strong technical support and reference for other similar large and medium-sized beam making yard.

precast beamintelligenttrussfolding device

姜登朋

展开 >

中铁十二局集团第一工程有限公司,西安 710038

预制梁 智能化 桁架式 收面装置

2025

价值工程
河北省技术经济管理现代化研究会

价值工程

影响因子:0.559
ISSN:1006-4311
年,卷(期):2025.44(1)