顶推施工中的落梁是指在连续梁顶推到位,拆除导梁,将主梁顶起,拆除顶推时的临时滑道装置,然后将主梁均匀地降落并安放在永久支座上的过程。采用顶推法施工的桥梁,落梁控制是一个影响到全桥施工控制成败的关键环节。落梁时各支座处应当同步落梁,因为此时的梁体已是连续体系,如果主梁的竖向位移出现任何偏差,即各支座处落梁不同步,都将在梁内产生附加内力。因此,针对本项目曲线钢箱梁顶推完成后具有落梁高度大的特点,开展基于落梁不同步的控制研究,探究落梁不同步的限值,提出落梁控制指标,优化落梁施工方案。
Falling Control Technology for Small Radius High Drop Curved Steel Box Girder
The falling beam in jacking construction refers to the process of pushing the continuous beam into place,removing the guide beam,lifting the main beam,removing the temporary sliding device during top pushing,and then uniformly lowering and placing the main beam on the permanent support.The control of beam drop is a key factor affecting the success or failure of the entire bridge construction control for bridges constructed using the top-down method.When the beam is dropped,all supports should be dropped synchronously,because the beam body is already a continuous system.If there is any deviation in the vertical displacement of the main beam,that is,if the beams are not dropped synchronously at all supports,additional internal forces will be generated inside the beam.Therefore,in response to the high drop height of the curved steel box girder in this project after the top push is completed,a control study based on asynchronous drop of the girder is carried out to explore the limit value of asynchronous drop of the girder,propose drop control indicators,and optimize the drop construction plan.

bridge engineeringjacking constructionfalling beamasynchronous

王高平

展开 >

中铁北京工程局集团第二工程有限公司,长沙 410000

桥梁工程 顶推施工 落梁 不同步

2025

价值工程
河北省技术经济管理现代化研究会

价值工程

影响因子:0.559
ISSN:1006-4311
年,卷(期):2025.44(1)