建筑技术2025,Vol.56Issue(1) :65-68.DOI:10.13731/j.jzjs.2025.01.0065

综合交通枢纽工程盖挖逆作法研究与应用

STUDY ON AND APPLICATION OF COVERED TOP-DOWN EXCAVATION IN COMPREHENSIVE TRANSPORTATION HUB ENGINEERING

侯朝 杨阳 刘泽宏 徐梓恒 刘占省 苏冠宏
建筑技术2025,Vol.56Issue(1) :65-68.DOI:10.13731/j.jzjs.2025.01.0065

综合交通枢纽工程盖挖逆作法研究与应用

STUDY ON AND APPLICATION OF COVERED TOP-DOWN EXCAVATION IN COMPREHENSIVE TRANSPORTATION HUB ENGINEERING

侯朝 1杨阳 2刘泽宏 1徐梓恒 2刘占省 2苏冠宏2
扫码查看

作者信息

  • 1. 中铁建工集团有限公司,100160,北京
  • 2. 北京工业大学城市建设学部,100124,北京
  • 折叠

摘要

基于北京城市副中心站综合交通枢纽工程的特殊地理位置和地质条件,本项目采用盖挖逆作法进行地下建筑的施工.首先对地下结构工程的施工方法进行了概述,基于项目实际工程情况对盖挖逆作的施工重难点进行分析,确定了合理高效的盖挖逆作施工顺序;其次对盖挖逆作工程中的土方开挖技术、基坑降水施工技术、基坑监测技术等进行创新改进,提高了工程效率的同时保证了安全度.此外,针对盖挖逆作塔式起重机基础施工技术进行改进,采用钢管桩式混凝土承台塔式起重机基础.最后,在盖挖逆作技术基础上结合BIM和AR技术进行了创新应用,推动了盖挖逆作工程的现代化发展.

Abstract

Considering the special geographical location and geological conditions of the comprehensive transportation hub project of Beijing Sub-Center Railway Station,covered top-down excavation was performed during the construction of underground structures.Firstly,the construction method for underground structural engineering was described.Key and difficult points of covered top-down excavation was analyzed based on engineering conditions and a reasonable and efficient construction sequence was determined for covered top-down excavation.Secondly,earthwork excavation,foundation pit dewatering and foundation pit monitoring involved in covered top-down excavation were improved for higher engineering efficiency and safety.Additionally,foundation construction with tower cranes were improved by using a steel pipe pile type concrete pedestal as a tower crane foundation.Finally,BIM and AR technologies were applied based on covered top-down excavation to advance the development of covered top-down excavation engineering.

关键词

盖挖逆作/副中心枢纽工程/塔式起重机基础施工

Key words

covered top-down excavation/sub-center hub engineering/tower crane foundation construction