Taking the super high-rise tower as an object,a closed and safe working space is provided for the construction of the vertical structure of the tower core tube by means of the intelligent lifting mould frame system.The installation height of the intelligent lifting mould base is 33.4 m.The installation principle of the steel platform is"Assembly on the ground and assembly in the air",and the installation principle of the hanger is"Three-span unit and unit hoisting".
关键词
超高层/智能顶升模架系统/钢平台系统/挂架系统
Key words
super high-rise/intelligent lifting die frame system/steel platform system/rack system