在城市轨道交通建设中,由于长距离、小半径盾构掘进情况越来越多,导致盾尾刷因长时间受力或受力不均而磨损,降低或失去密封性,需对其及时进行更换。本研究以苏州轨道交通 8 号线虎殿路站—虎丘湿地公园站出入场线区间更换盾尾刷为背景,基于盾尾刷更换各种止水方式比选分析,结合该工程位于软弱局部透水地层特点,提出并实施了一种多方式注浆止水的盾尾刷更换方法。即在软弱局部透水地层中,通过在盾尾注入聚氨酯、惰性浆液、双浆液,以及通过盾体径向注入惰性浆液,对盾尾前后地下水进行有效封堵,再通过拆卸一环管片进行第一道盾尾刷的拆卸与更换,更换期间实测表明地表累积沉降与日沉降均满足控制要求,注浆加固后打开观测孔止水效果良好,仅耗时 14d便恢复掘进。本研究提出的软弱局部透水地层注浆止水的盾尾刷更换成套工艺与方法取得很好的实施效果,可为今后类似工程提供参考。
Study on the replacement technology of shield tail brush by grouting for water plugging in weak and locally permeable stratum
In the construction of urban rail transit,due to the increasing number of long-distance and small-radius shield tunneling,the shield tail brush is worn because of in the long-time or uneven stressed state,which reduces or loses its sealing property,so it needs to be replaced in time.This study took the shield tail brush replacement project of the en-trance and exit line interval between Hudian Road Station and Huqiu Wetland Park Station of Suzhou Rail Transit Line Eight,as engineering background to analyze and compared the characteristics and applicable conditions of different water plugging methods based on various water plugging methods that can be used in the replacement of the shield tail brush.We combines with the fact that the project was located in the weak and locally permeable stratum to put forward and implement a replacement method of shield tail brush by multi-method grouting for water plugging.This method effectively seals off groundwater before and behind the shield tail by injecting polyurethane slurry,inert slurry and ce-ment-waterglass double slurry into the soil behind the shield tail,as well as by radially injecting inert slurry through the shield body into weak and locally permeable stratums.Then the first shield tail brush was replaced by tearing down the last ring of pipe segment to expose the first shield tail brush.At the same time,during the replacement of the shield tail rear pipe segment longitudinal tie,the jack support and other ways maintained stability.This replacement method provided a complete set of process and method for replacing the shield tail brush by grouting for water plug-ging in weak and locally permeable stratum.During the replacement of the shield tail brush,the measured surface data showed that the cumulative settlement of the surface and the daily settlement meet the control requirements.After the grouting reinforcement,the observation holes on the pipe segment were opened,and it was found that the effect of water plugging effect was satisfactory.It only took 14 d to resume tunneling,and better implementation results had been achieved,which could provide reference for similar projects in the future.

shield tunnelweak and locally permeable stratumshield tail brush replacementa variety of slurry cross groutinggrouting for water plugging

丁程、程姿洋、王文恺、杨平

展开 >

南京林业大学土木工程学院,南京 210037

中交一公局第八工程有限公司,天津 300170

盾构隧道 软弱局部透水地层 盾尾刷更换 多种浆液交叉注浆 注浆止水

住建部科学研究项目

2017-K4-017

2024

林业工程学报
南京林业大学

林业工程学报

CSTPCD北大核心
影响因子:0.742
ISSN:2096-1359
年,卷(期):2024.9(2)