煤炭科学技术2024,Vol.52Issue(9) :68-75.DOI:10.12438/cst.2024-0816

煤矿复杂地层TBM掘进巷道新型装配式支护结构工程实践

New prefabricated support structure for TBM tunneling in complex strata of coal mines:engineering practice

唐永志 唐彬 程桦 王传兵 王要平
煤炭科学技术2024,Vol.52Issue(9) :68-75.DOI:10.12438/cst.2024-0816

煤矿复杂地层TBM掘进巷道新型装配式支护结构工程实践

New prefabricated support structure for TBM tunneling in complex strata of coal mines:engineering practice

唐永志 1唐彬 2程桦 2王传兵 3王要平3
扫码查看

作者信息

  • 1. 安徽理工大学土木建筑学院,安徽淮南 232001;淮南矿业(集团)有限责任公司,安徽淮南 232001
  • 2. 安徽理工大学土木建筑学院,安徽淮南 232001
  • 3. 淮南矿业(集团)有限责任公司,安徽淮南 232001
  • 折叠

摘要

TBM(Tunnel Boring Machine)全断面掘进机已在煤矿深井巷道掘进工程中成功应用,取得了显著的社会经济效益.但仍存在影响其进一步推广应用的技术瓶颈.针对当前支护结构与支护技术难以同时满足支护效率、支护强度和施工成本方面的要求,TBM难以充分发挥其速度优势的技术瓶颈,研究团队研发了新型钢管片型装配式支护结构.开展了新型装配式支护结构大比尺模型试验,获得新型支护结构在受载条件下变形破坏规律,根据试验结果优化新型支护结构型式.基于新型钢管片支护下TBM掘进巷道数值模拟评估新型支护结构可靠性.最后开展工业性试验,现场验证新型钢管片式支护结构用于煤矿TBM掘进巷道的可行性.试验结果表明,巷道围岩最大拉应变为803×10-6,钢管片支护结构变形量小于 1 mm.新型支护结构安装速度快,可在 90 min内掘进 1.5 m并完成一环管片的安装工作,显著提高了TBM掘进巷道的支护强度和TBM掘进作业线的地层适应性.为未来进一步提高煤矿巷道掘进速度、保障煤矿采掘接替提供技术参考.

Abstract

Tunnel Boring Machines(TBMs)have been successfully applied in the excavation of deep shaft roadways in coal mines,yield-ing substantial socio-economic benefits.However,technical bottlenecks remain that hinder their further promotion and application.In re-sponse to the challenge of current support structures and techniques failing to simultaneously meet the requirements of support efficiency,strength,and construction costs,which impedes the full utilization of TBM speed advantages,a research team has developed a novel steel pipe segment assembly support structure.Large-scale model tests of the new prefabricated support structure were conducted to ascertain the deformation and failure patterns under loaded conditions,and the support structure was optimized based on the test results.Numerical simulations were performed to evaluate the reliability of the new support structure under TBM tunneling conditions.Industrial trials were subsequently conducted to field-test the feasibility of the new steel pipe segment support structure for TBM-excavated roadways in coal mines.The test results indicate that the maximum tensile strain of the surrounding rock is 803 με,and the deformation of the steel pipe support structure is less than 1 mm.The new support structure can be installed quickly,with the installation of one ring of segments(1.5 m)completed within 90 minutes,significantly enhancing the support strength in TBM-excavated roadways and the adaptability to strata conditions.This research provides a technical reference for further increasing the tunneling speed of coal mine roadways and ensuring the continuity of coal mining operations.

关键词

巷道掘进/全断面掘进机/复杂地层/TBM掘进/装配式支护结构

Key words

tunnel excavation/Tunnel Boring Machine/complex strata/TBM tunneling/fabricated support structure

引用本文复制引用

基金项目

国家自然科学基金资助项目(51804006)

安徽省自然科学基金面上资助项目(2208085ME118)

出版年

2024
煤炭科学技术
煤炭科学研究总院

煤炭科学技术

CSTPCDCSCD北大核心
影响因子:2.095
ISSN:0253-2336
参考文献量20
段落导航相关论文