南水北调与水利科技(中英文)2024,Vol.22Issue(6) :1189-1195,1213.DOI:10.13476/j.cnki.nsbdqk.2024.0118

滨海枢纽北船闸输水系统阀门运行方式

Operation mode of valves in water conveyance system of North Ship Lock of Binhai hub

王铁力 陈莹颖 金晓宇 缪树杰 沈昊 杨帆
南水北调与水利科技(中英文)2024,Vol.22Issue(6) :1189-1195,1213.DOI:10.13476/j.cnki.nsbdqk.2024.0118

滨海枢纽北船闸输水系统阀门运行方式

Operation mode of valves in water conveyance system of North Ship Lock of Binhai hub

王铁力 1陈莹颖 2金晓宇 3缪树杰 4沈昊 1杨帆3
扫码查看

作者信息

  • 1. 江苏省水利勘测设计研究院有限公司,江苏扬州 225127
  • 2. 水利部交通运输部国家能源局南京水利科学研究院,南京 210029
  • 3. 扬州大学水利科学与工程学院,江苏扬州 225009
  • 4. 江苏省江都水利工程管理处,江苏扬州 225299
  • 折叠

摘要

滨海枢纽北船闸为淮河入海水道与通榆河间通航永久性建筑物,通过物理模型试验,分析在不同阀门开启时间船闸输水系统的物理指标,重点探究输水过程的水力特性、闸室内流态和输水廊道顶部的压力变化特性以及闸室的船舶停泊条件.结果表明:该船闸在运行水头不大于5.99 m时,充水阀门双边匀速连续开启的时间为7 min,而当运行水头大于5.99 m时,充水阀门双边匀速连续开启的时间为9 min;在各运行水位组合时,泄水阀门双边匀速连续开启的时间均为7 min.在推荐的阀门运行方式下,船闸输水水力特性、输水廊道压力特性和闸室船舶停泊条件等均满足规范和设计要求.

Abstract

The North Ship Lock of Binhai hub is a permanent structure for navigation between Huaihe River and Tongyu River with the ship lock level of grade Ⅱ.The design of normal water level difference requires the water conveyance time to be 6~8 min.The design of high water level difference(5.99 m and 7.19 m head difference)requires the water conveyance time to be 9~12 min.The ship lock is subjected to two-way head action with the maximum forward water level difference of 7.19 m,and the maximum reverse water level difference of 1.91 m.To construct the ship lock the operation safety and water conveyance efficiency of the ship lock are the key technical problems to be solved.In order to ensure the safe and efficient operation along with providing technical references for the safe and reliable operation of the ship lock,the physical model test was used to study the hydraulic characteristics of the centralized water conveyance system of the North Ship Lock of the Binhai hub.According to the provisions and requirements of the"Design Code for filling and Emptying Systems of Shiplocks(JTJ 306-2001)"and the"Technical Code of Modelling Test for Port and Waterway Engineering(JTS/T 231-2021)",the weight and force scale of the original model was 27000,the flow velocity and time scale was 5.48,and the flow scale was 4 929.5.The overall physical model of the ship lock with a scale of 1∶30 was established.The side wall of the lock chamber,the water conveyance corridor and the inlet and outlet sections of the upper and lower lock heads were all made of polyethylene plastic plates.Reservoirs were set up in both upstream and downstream,and 2.3 m×2.5 m horizontal grooves were arranged in the reservoir to stabilize the upstream and downstream water levels.The hydraulic characteristics of the water conveyance process of the lock,the flow pattern in the lock chamber,the pressure change characteristics at the top of the water conveyance corridor and bollard force for ships moored in lock chambers under different valve opening time were analyzed by experiments,and the rationality of the overall layout design of the water conveyance system was verified.When the operating head was not greater than 5.99 m,the continuous opening time of the double-sided uniform speed of the filling valve is 7 min.When the operating head was greater than 5.99 m,the continuous opening time of the double-sided uniform speed of the filling valve is 9 min.In each operating water level combination,the continuous opening time of the double-sided uniform speed of the discharge valve is 7 min.When the upper lock head valve was continuously opened bilaterally for water filling for 6 to 9 min,the minimum instantaneous pressure at the top of the upper lock head water conveyance corridor was 2.57 mH2O.When the lower lock head valve was continuously opened bilaterally for water discharge for 6 to 9 min,the minimum instantaneous pressure at the top of the lower lock head water conveyance corridor was-0.26 mH2O.Under different water head conditions,the water level of the lock chamber rose and fell smoothly,the surface was calm,and there was no unfavorable flow pattern such as vortex and bubble vortex in the lock chamber,and as a whole flow pattern of the lock chamber was better.Under the recommended valve operation mode,the hydraulic characteristics of the lock,the pressure characteristics of the water conveyance corridor and bollard force for ships moored in lock chambers meet the specifications and design requirements.

关键词

北船闸/输水系统/水力特性/瞬态压力/模型试验

Key words

North Ship Lock/water conveyance system/hydraulic characteristics/instantaneous pressure/model test