首页|电化学储能电站接入电网测试方法

电化学储能电站接入电网测试方法

扫码查看
随着高比例新能源接入,电网的安全稳定运行面临着巨大的挑战.当电网出现有功缺额等问题时,新能源场站功率控制精度、响应时间等相关指标不满足要求,不能快速参与电网调峰及系统电压频率的调节,因此,介绍了电化学储能电站接入电网的测试方法,并针对测试过程中通信配置不合适导致报文拥堵,装置收到指令时间不同步引起响应时间过长、功率调节不到位等问题,通过修改"报文采集步长",优化整改措施.结果表明提出的系列测试方法可有效解决测试过程中出现的响应时间过长、功率调节不到位等问题,显著提升储能电站接入电网的测试效率.
Testing methods for connecting electrochemical energy storage stations to the power grid
With the increasing integration of renewable energy sources,the safe and stable operation of the power grid faces significant challenges.When issues such as active power deficits arise,the precision of power control and response time of renewable energy stations do not meet requirements,hindering their ability to quickly participate in peak shaving and regulate voltage and frequency within the grid.This paper elaborates on the testing methods for connecting electro-chemical energy storage stations to the power grid.It addresses issues such as inappropriate communication configura-tions and unreasonable software logic during testing,proposing corresponding optimization measures like"stop upon reaching limits."Validation of these measures shows that the proposed series of testing optimizations can effectively resolve problems related to excessive response times and inadequate power regulation during testing,significantly enhan-cing the efficiency of testing for energy storage stations connected to the power grid.

energy storage stationactive powerreactive power

马兵、刘刚、张文、孙大伟、周玫

展开 >

宁夏电力能源科技有限公司,宁夏银川 750011

国网宁夏电力有限公司营销服务中心(国网宁夏电力有限公司计量中心),宁夏银川 750011

储能电站 有功功率 无功功率

2024

宁夏电力
宁夏电力科技教育工程院 宁夏电机工程学会

宁夏电力

影响因子:0.286
ISSN:1672-3643
年,卷(期):2024.(6)