首页|建成未投产管道内腐蚀原因分析及完整性管理方法研究

建成未投产管道内腐蚀原因分析及完整性管理方法研究

扫码查看
目前,国内已发生多起建成未投产输油管道在放置一段时间后,在即将投产前的试压过程中发生泄漏的事故.经分析,管道泄漏形式均为内腐蚀穿孔.产生内腐蚀的原因为管道建成试压扫水后,未进行干燥处理且封存及后续管理措施不到位,使得管道内壁发生腐蚀.经国内外相关标准对比分析,发现国内现有施工方法的不足,并结合国内外相关标准和及施工单位先进做法,从管道清洁处理措施、压力试验、干燥和封存、延迟投产期间检测和监测四个方面给出延迟投产管道内腐蚀防控方法,为延迟投产管道的失效预防和完整性管理提供参考.
Analysis of Corrosion Causes in Delayed Operation Pipeline and Research on Integrity Management Methods
Currently,there have been multiple accidents in China where oil pipelines that have not been put into operation have leaked during the pressure testing process before being put into operation after being placed for a period of time.The reason for internal corrosion is that the pipeline was not dried after pressure testing and water sweeping,and the sealing and subsequent management measures were not perfect,resulting in corrosion on the inner wall of the pipeline.After comparing and analyzing relevant domestic and foreign standards,it was found that there are shortcomings in existing construction methods in China.Based on relevant domestic and foreign standards and advanced practices of construction units,corrosion prevention and control methods for delayed operation pipelines were proposed from four aspects:pipeline cleaning measures,pressure testing,drying and sealing,and detection and monitoring during delayed operation,providing reference for failure prevention and integrity management of delayed operation pipelines.

internal corrosiondelayed operationcleaning treatmentpressure testingdryingsealing

刘磊、单新煜、毕逢东、冯世忠、卢楠、董国亮、任国琪

展开 >

中国石油天然气股份有限公司天然气销售分公司,北京 100101

中国石油天然气股份有限公司天然气销售分公司甘肃燃气公司,甘肃 兰州 730000

中国石油天然气股份有限公司天然气销售分公司哈尔滨中庆公司,黑龙江 哈尔滨 150000

中国石油集团工程材料研究院有限公司,陕西 西安 710077

展开 >

内腐蚀 延迟投产 清洁处理 试压 干燥 封存

2024

全面腐蚀控制
中国工业防腐蚀技术协会

全面腐蚀控制

影响因子:0.278
ISSN:1008-7818
年,卷(期):2024.38(9)