首页|基于定额回归法的导流洞工程赶工费用计算

基于定额回归法的导流洞工程赶工费用计算

扫码查看
导流隧洞施工受水文、地质、施工环境等不确定性因素影响,常出现工期延误需进行赶工.针对水电站导流洞施工过程中的单一工期延误事件,分析了常见的变更方案及对应的理论延误工期确定方法,提出一种基于定额回归法的导流洞工程赶工费用计算方法,并将该方法应用于白鹤滩水电站导流洞施工中.结果表明,该方法能确定各延误事件与工序影响的对应关系,判别非承包商责任的工期延误和赶工事实,并计算出完整的赶回工期、赶工工序及赶工费用,为工程索赔提供了参考依据.
Acceleration Cost Calculation for Diversion Tunnels Based on Quota Regression Analysis
The construction of diversion tunnels is affected by uncertain factors such as hydrology,geology,and envi-ronment,so contractors are always required acceleration caused by projects delay.Aiming at the single project delay event of the diversion tunnel of hydropower station,the engineering change plans and their theoretical delay period were dis-cussed.A method that calculates acceleration costs based on the quota regression analysis was proposed.A diversion tun-nel case of Baihetan Hydropower Station show that this method can determine the relationships between each delayed e-vent and the influence of processes,and identify the fact that the contractor is not responsible for the delay and accelera-tion as well as calculate complete acceleration time,processes and costs,which provide a basis for engineering claims.

diversion tunnelsacceleration costquota regression analysisclaimhydropower station construction

刘乐、刘潋、黄建文、刘敏、张光飞

展开 >

三峡大学水利与环境学院,湖北宜昌 443002

三峡大学水电工程施工与管理湖北省重点实验室,湖北宜昌 443002

国家能源集团大渡河流域水电开发有限公司,四川成都 610000

中国三峡建工(集团)有限公司,北京 101100

展开 >

导流洞 赶工费 定额回归法 索赔 水电站施工

国家自然科学基金项目水电工程施工与管理湖北省重点实验室开放基金

518791472020KSD12

2024

水电能源科学
中国水力发电工程学会 华中科技大学 武汉国测三联水电设备有限公司

水电能源科学

CSTPCD北大核心
影响因子:0.525
ISSN:1000-7709
年,卷(期):2024.42(1)
  • 8