首页|直界水库增容工程水土流失预测及防治对策

直界水库增容工程水土流失预测及防治对策

扫码查看
水库工程建设中普遍存在水土流失问题,不仅破坏了原有库区岩土结构的稳定性,还给周边生态环境带来不利影响.文章以直界水库增容工程为例,对水库建设过程中可能造成的水土流失现象进行分析预测,合理划分防治责任范围和分区,确定水土流失防治措施,以减少因工程建设施工造成的水土流失.
Soil and Water Loss Prediction and Control Measures for the Capacity Increase Project of Zhijie Reservoir
Water and soil loss is a common problem in the construction of reservoir projects,which not only destroys the stability of the original geotechnical structure of the reservoir area,but also brings adverse effects on the surrounding ecological environment.Taking Zhijie Reservoir capacity increase project as an example,this paper analyzes and predicts the possible soil and water loss phenomenon in the process of reservoir construction,reasonably divides the control responsibility scope and zoning,and determines the control measures of soil and water loss,so as to reduce the soil and water loss caused by the construction of the project.

Zhijie reservoirSoil and water lossComprehensive treatment

李宝东

展开 >

山东省海河淮河小清河流域水利管理服务中心,山东济南 250014

直界水库 水土流失 综合治理