山东水利2024,Issue(9) :49-51.

谈刨铣法连续式高喷防渗墙施工技术

Discussion on Construction Technology of Planer Milling Continuous High Spray Cutoff Wall

王雅波 粘斌
山东水利2024,Issue(9) :49-51.

谈刨铣法连续式高喷防渗墙施工技术

Discussion on Construction Technology of Planer Milling Continuous High Spray Cutoff Wall

王雅波 1粘斌1
扫码查看

作者信息

  • 1. 济南市水利工程服务中心,山东济南 250000
  • 折叠

摘要

随着我国水利工程建设的快速发展,高喷防渗墙施工技术日益受到重视.这项新兴的工艺具有极高的应用价值和经济效益.水利工程中的刨铣法连续式高喷防渗墙施工技术是一项先进的、有效的施工方法,这项技术主要采用刨铣机工作原理,将防渗材料直接喷射到墙体表面,可以起到很好的防渗效果.

Abstract

In our country,with the rapid development of water engineering construction,the construction technology of high spray cutoff wall has been paid more and more attention.This emerging technology has a very high application value and economic benefits.The planer milling continuous high spray cutoff wall construction technology is an advanced and effective construction method,with the working principle of the planer milling machine,the anti-seepage material directly sprayed to the surface of the wall,playing a fine anti-seepage effect.

关键词

水利工程/刨铣法/连续式/高喷防渗墙施工

Key words

Water project/Planer milling method/Continuous type/High spray cutoff wall construction