长沙冰雪世界百米深矿坑施工电梯设计优选与施工实践

扫码查看
长沙冰雪世界工程以百米深矿坑为载体,岩壁陡峭,坡角为80°~90°不等.项目部通过2种设计方案的比选,即常规附着式施工电梯和间接附着式施工电梯的设计方案,确定间接附着式施工电梯为最优设计方案,并运用MIDAS/Gen建立模型,进行强度、刚度、稳定性的分析.同时,项目部运用BIM技术形象直观地展示间接附着式施工电梯的施工工艺流程.此最优设计方案有效解决了人员及少量材料垂直运输的问题,大大提高了施工和管理的效率.
Design Optimization and Construction Practice of Construction Elevator 100-meter-depth Excavation in the Changsha Ice and Snow World
Changsha Ice and Snow World project stands on the 100-meter-depth excavation with steep cliff of 80°~ 90°.By comparing two different design options between conventional attachment and indirect attachment,indirect attachment is employed as the optimal design.Finite element model is established by MIPAS/Gen to analyze the strength,stiffness and stability.Besides,construction process flow of construction hoist with indirect attachment is described by using BIM technology.The adopted design option is proved to efficiently solve the problem about the vertical transportation of workers and minority of material,and also highly improve the construction and management efficiency.

foundationselevatorconventional attachmentindirect attachmentBIMdesignconstruction

郭朋鑫、谭立新、蒋立红、林冰、黄虎

展开 >

中国建筑第五工程局有限公司,湖南 长沙 410004

中国建筑股份有限公司技术中心,北京 100037

基坑 电梯 常规附着式 间接附着式 建筑信息化模型 设计 施工

2017

施工技术(中英文)
亚太建设科技信息研究院 中国建筑设计研究院 中国建筑工程总公司 中国土木工程学会

施工技术(中英文)

影响因子:1.244
ISSN:2097-0897
年,卷(期):2017.46(8)
  • 6
  • 3